Case Histories
Reporting Service
Problem Stepped and Staggered Gable Abutments
Location:
South Devon, UK.
Hourly mean wind speed category; 22 metres per
second.
Category of exposure to wind driven rain / spell
indices; 100+
Topography category; Shallow.
External skin; Clay brick to BS 3921, frogs up.
Cavity width; 50mm
Mortar 1:1:5.5 by volume, weathered tooled joints.
National NHBC registered house builder engaged
upon large housing development.
Stepped and staggered gable abutments throughout the site,
constructed using a proprietary tray system with lead flashing attached.
Problem
Considerable dampness witnessed in party walls below
stepped tray arrangement to some abutments.
Action
Initially the house builder contacted the manufacturer,
but the dampness problem was not solved.
The seriousness of the situation prompted urgent
attention, and a decision was made by the house builder to remove the
existing trays from the troublesome gables and replace them with a different
proprietary make. Replacement trays were thus obtained from a different
(second) manufacturer.
Following the second installation, the problem persisted
and the gables remained damp.
The house builder then contacted a third manufacturer -
Cavity Trays Ltd of Yeovil.
Cavity Trays carried out a survey of all the problem
gables on site and advised the contractor of its findings. The contractor
accepted the submissions and made the decision to execute the work yet again,
but this time using Cavity Trays of Yeovil preformed warranted Type X
cavitrays.
Installation of the Type X trays resulted in the
dampness problem being eliminated.
What originally went wrong?
Analysis regarding the initial installation is not
possible, as the problematic gables had already been replaced once before
Cavity Trays was contacted. However, inspection of the removed trays
originally incorporated suggested capillary action may have been one of
several reasons for failure?
Features to interrupt the capillary path are recognised
as essential features when executing construction details. Incorrect or
inadequate bedding can act as a catalyst in saturated masonry walls, and
water permitted to reservoir the bedding course can transgress adjoining
masonry. In any stepped abutment, a saturated brick within a tray must be
prevented from contacting (and therefore soaking into) the inboard masonry.
The end upstand of the tray must provide isolation. If the upstand height is
insufficient or is bridged by mortar, dampness will track inwardly. (See conclusion)
It is possible the second installation might have been
more successful had the cavity upstands (the part of the tray that should
rise in the cavity by 150mm minimum) suited the actual cavity width to a
greater extent? The fixed dimension trays used meant the full width was not
protected whenever the cavity width technically went over-size. It should not
occur, but in reality it often does.

It was also noted the size of the lead flashing attached
to each tray did not match the length of the tray but was far shorter. It was therefore queried to what extent
flashings lapped and whether wind-driven rain had been driven between? When
built in following the roofline pitch, small lead flashings offer less
overlap protection against wind-driven rain than larger flashings.
Examples of trays with flashings that do not match
the full length of the tray.
Cavity Trays Ltd recommended use of warranted Type X
cavitrays - which have high exposure rating. Supplied with attached code 4
lead flashings, the trays benefit anti-capillary tracking measures to their
base, plus a flexible isolation integrity barrier to the end upstand, to
prevent dampness being inboard transmitted. The main cavity upstands also
adjust to take up the maximum cavity width encountered, thus addressing
variances. Importantly, the size of each attached lead flashing matches the
length of the tray, and the lap (and subsequent barrier protection against
wind-driven rain) is greater that that witnessed on the alternative products.
To achieve dry status the contractor had in total
purchased three different types of product from three different
manufacturers. Thus three costs for materials, three costs for operatives
labour, and three costs for use of scaffolding, plant etc. Because the gables failed to achieve dry
status at the first and second installations, the contractor also experienced
considerable loss of confidence with the purchasers of the properties
affected.
Conclusion
Perhaps the first and second installations might not
have proved troublesome on a less exposed site? How can one be sure? In
reality one cannot – so it is always prudent to build in anticipation of
severe weather conditions. Warranted high exposure rated trays are generally
no more expensive than alternatives. The trays that stopped the damp
penetration problems were Type X trays from Cavity Trays of Yeovil, and
interestingly Cavity Trays is the only tray manufacturer awarded European
Technical Approval. The Company also holds LABC Local Authority Building
Control Product Type Approval.
Type X trays are also accompanied with product
performance liability protection for the benefit of Architect, Builder and
Client.
One prices to execute any job just once, - and this was
clearly a costly exercise for the contractor concerned. On any site,
identical properties will behave in different ways. Use of high exposure rated products with integral features
provides peace of mind.
Thorough product selection is of paramount importance.
Adherence to that selected specification can enable one to get it right –
first time.
This
article was compiled using information provided by the contractor and Cavity
Trays Ltd and was originally published in a revised format by Cavity Trays
Ltd in 2002.
|